Project duration:

4 weeks

Client:

Global supplier of pigment.

Project summary:

Our client had carried out significant modifications to a previously CE Marked machine, including improvements to guarding and installation of a new electrical control system. This necessitated a confirmation of the machines safety related design, hence a PUWER assessment was performed.

Applicable Legislation:

Work Equipment Directives (implemented in UK as the Provision and Use of Work Equipment Regulations).

What we did:

  • Carried out an assessment of the modification work against PUWER regulations albeit largely in-line with Essential Requirements of CE marking directives.
  • Provided a detailed report listing improvement suggestions and non-compliances with photographic support and guidance on rectification work.
  • Provided guidance and assistance with preparation of new user documentation.

What the customer did:

  • Supplied us with detailed mechanical and electrical design drawings for the modifications.
  • Modified the design according to our recommendations.
  • Recorded details of compliance and satisfied legal obligations.

Final outcome:

Client satisfied their legal obligations under PUWER and now holds documentary evidence to justify.

How Can We Help You?

Ask a question, or request a callback.
Please type your full name.

Invalid Input

Invalid email address.

Invalid Input

Invalid Input

Invalid Input

Please make a selection

Invalid Input

From time to time we would like to send you our newsletter. If you consent to us contacting you for this purpose please tick the following box. (Privacy Policy)
From time to time we would like to send you our newsletter. If you consent to us contacting you for this purpose please tick the following box. <a href="/privacy-policy-and-cookies-statement" target="_blank">(Privacy Policy)</a>
Invalid Input