Published 29/06/23
The long and the short of it is that no-one in the UK government or civil services sees any need to rush into amending the UK’s Supply of Machinery (Safety) Regulations. Currently there are other priorities which include the possibility of a trade agreement with the EU. This could include a mutual recognition agreement for certification and accreditation bodies which would have a major impact on the activities of Notified and Approved Bodies. The UK is also in the process of a root and branch review of its product safety legislation. The shape of things to come is still unclear but proposals for change should certainly crystalise well before the end of the three and a half years in which manufacturers are required to implement the new requirements of the Regulation. So here is some educated guess work:
- The UK will do nothing at all until the Machinery Regulation is published in the Official Journal.
- In the first instance, we don’t think that there are any changes brought about by the Regulation which will actually make machinery less safe under the Regulation in in the EU than it currently is under the Machinery Directive, so the short-term answer is that the CE marking will remain as a valid alternative to the UKCA Mark until at least the current deadline for the implementation of the UKCA mark, whether the CE mark is applied under the Directive or the Regulation.
- The UK will not adopt the Regulation into UK statute; it will continue to transpose it into a UK statutory instrument.
- There will not be exact regulatory alignment between the UK and the EU although we think the EHSRs probably will be common.
- However, the administrative provisions, and in particular the requirements for the engagement of a Notified Body for all machines listed Annex 1 will not become part of UK law.
This will allow the UK Government to say to machinery manufacturers in the UK “Look: Brexit has allowed us to save you the costs of a third party assessment” ignoring the fact that any manufacturer who wants to sell Annex 1 machinery into the EU (including Northern Ireland) will now need to engage a Notified Body, but that will be more expensive than it was before because they will have to deal with someone based in the EU and the number of UK Approved Bodies will have reduced because there is no longer a viable business model for their activities in the UK.
Deadlines for particular aspects of the new European Machinery Regulation:
|
14 June 2023 |
Regulation finalised (date at end of Article 54) |
| 29 June 2023 |
Regulation published in the Official Journal |
| 19 July 2023 |
Regulation enters into force (20 days after publication) Article 6(7) (adding new machinery to Annex I) and Articles 48 (Committee procedure) and 52 (Transitional provisions) apply |
| 20 January 2024 |
Articles 26 to 42 (Chapter V: Notification of Conformity Assessment Bodies) apply |
| 20 July 2024 |
Article 6(2) to (6), (8) and (11) (Annex I machines) and Articles 47 (Exercise of the delegation) and 53(3) (Evaluation and review; Annex I) apply First implementing act of Article 6(10) is due |
| 20 July 2025 |
Article 6 (Annex I procedures) § 9 (data and information) applies |
| 20 July 2026 |
Article 53(3): report required on Article 6 (Annex I procedures) (4) and (5), and every five years thereafter |
| 20 October 2026 |
Article 50 (Penalties): member states must notify the Commission of rules and measures by this date |
| 20 January 2027 |
Regulation fully applies (Article 54) 2006/42/EC is repealed (Article 51) Machines in conformity with 2006/42/EC can no longer be prevented from being placed on the market (Article 52) |
| 19 July 2028 |
Article 47(2) (adopting delegated acts) ends |
| 20 July 2028 |
Article 53(1) requires a public report on the evaluation and review of the Regulation (and every four years after) |